NEW QUESTION 46
Safety Stock outputs from Multistage Inventory Optimization are sent to which of these processes? Note:
There are 2 correct answers to this question.
- A. Decoupling Points determination in SAP IBP for demand-driven replenishment
- B. Charts creation in SAP Supply Chain Control Tower
- C. Supply Heuristics in SAP IBP for sales and operations
- D. Demand Sensing with Gradient Boosting (Full)
Answer: C,D
NEW QUESTION 47
NO.21 For which of the following application jobs can you enter planning filters as parameters? Note:
There are 2 correct Answers to this question.
- A. Purge Non-Conforming Data
- B. Purge Master Data
- C. Create Time Periods for Time Profiles
- D. Purge Key Figure Data
Answer: B,D
NEW QUESTION 48
Which of the following modes can you use when creating a constrained plan? Note: There are 2 correct Answers to this question.
- A. Profit maximization
- B. Delivery maximization
- C. Resource maximization
- D. Production maximization
Answer: A,B
NEW QUESTION 49
What are the ways to achieve rolling aggregation with SAP IBP?
- A. Using a attribute as a key figure
- B. Using a appropriate period weight factor
- C. Using a key figure calculation
- D. Using a local member
Answer: B
NEW QUESTION 50
You are modeling a substitution scenario associated with a promotion. What are some of the Master Data parameters that you need to maintain to ensure desired results generated by the optimizer? Note:
There are 2 correct Answers to this question.
- A. Promotion duration
- B. Loc-Prod Subst Valid-From Date
- C. Location Product Sub Cost Rate
- D. Flag 'Disable Substitution of Location Products
Answer: A,B
NEW QUESTION 51
SAP IBP ensures interoperability with which applications?Note: There are 2 correct answers to this question.
- A. Salesforce Sales Cloud
- B. Financial Planning in SAP Analytics Cloud
- C. User management in SAP Success Factors
- D. Business Network in SAP Ariba
Answer: B,D
NEW QUESTION 52
You are adding a value-based filter to a planning view. Which of the following conditions apply? Note:
There are 3 correct Answers to this question.
- A. The alerts dashboard is not available if a value-based filter is set for the open planning view.
- B. These filters are always applied based on the values stored in the database.
- C. You can only apply one value-based filter per planning view.
- D. You can add (or delete) planning objects to a planning view after these filters are applied.
- E. These filters can be used together with attribute totals in the same planning view.
Answer: A,B,C
NEW QUESTION 53
What are the S&OP operator (optimizer) parameters associated with demand fair share?
- A. Number of fair share segments Maximum days of coverage Number of fair share segments late delivery
- B. Number of fair share segments Additional tiering costs (default) Inventory days of supply
- C. Number of fair share segments Additional tiering costs (default) Maximum inventory
- D. Number of fair share segments Additional tiering costs (default) Number of fair share segments late delivery
Answer: D
NEW QUESTION 54
You are using the Resource Location master data type. How do you specify capacity supply as time- dependent?
- A. Set the Capacity Supply Time Series indicator in the Resource Location master data type.
- B. Set the Capacity Supply additional attribute in the time profile.
- C. Set the Capacity Supply Time Series indicator attribute as a key.
- D. Maintain the CAPASUPPLY key figure values in the planning area.
Answer: A
NEW QUESTION 55
You are starting a new implementation project for SAP IBP and are considering the possible system architecture.What are the possible approaches for setting up the system landscape?Note: There are 2 correct answers to this question.
- A. Create additional planning areas in the test system to support training needs.
- B. Set up a two-tier landscape, and have the configuration of the development system regularly updated from the production system.
- C. Set up a three-tier landscape using transport, starting from the development system to test and production.
- D. Create additional test planning areas in the production system to support cutover needs.
Answer: B,C
NEW QUESTION 56
Which of the following are features of lag-based snapshots?Note: There are 2 correct answers to this question.
- A. Target key figures for these snapshots are exposed to the user in planning views.
- B. Lag-based snapshots are created in the Configuration app for a fixed time range.
- C. The number of lag-based snapshots are limited to nine levels.
- D. Target key figures for these snapshots must have lag as a root attribute in its base planning level.
Answer: B,D
NEW QUESTION 57
While modeling costs for optimization, you are conscious of the necessity to respect inventory targets and meet demands in the short term. Which of the following are valid relationships between costs you must adhere to? Note: There are 2 correct Answers to this question.
- A. Target inventory violation cost should be less than max inventory violation cost.
- B. Target inventory violation cost should be greater than inventory holding cost rate.
- C. Target inventory violation cost should be less than transportation cost rate.
- D. Target inventory violation cost should be greater than discount for demand lateness.
Answer: B,C
NEW QUESTION 58
When can filter blocks appear in calculations? Note: There are 2 correct Answers to this question.
- A. When using IFISNULL statements in the formula
- B. When modeling attribute as a key figure
- C. When modeling cross-period calculations
- D. When modeling attribute transformations
Answer: C,D
NEW QUESTION 59
You have set up a planning area and data is available. You adjust the necessary time profile settings and run the consistency check. Which settings can you change and still run a successful consistency check?
Note: There are 2 correct Answers to this question.
- A. Change the description of the attributes in the time profile.
- B. Change the past and future horizon of the levels in the time profile.
- C. Remove an attribute assigned to the time profile level if the attribute is used in a planning level.
- D. Add a new time profile level to the time profile.
Answer: A,B
NEW QUESTION 60
You run a what-if analysis and use the scenario planning function. Which actions can you perform? Note:
There are 3 correct Answers to this question.
- A. Run a scenario-specific inventory optimization job.
- B. Change scenario-specific master data.
- C. Run a scenario-specific demand sensing job.
- D. Share data with other users.
- E. Display data in analytics.
Answer: A,D,E
NEW QUESTION 61
Which applications are present in the sample model SAPIBP1?Note: There are 3 correct answers to this question.
- A. Demand Driven Replenishment
- B. Demand Sensing
- C. Inventory Optimization
- D. Response Planning
- E. Sales and Operations Planning
Answer: B,C,E
NEW QUESTION 62
For which of the following application jobs can you enter planning filters as parameters?Note: There are 2 correct answers to this question.
- A. Purge Non-Conforming Data
- B. Purge Master Data
- C. Create Time Periods for Time Profiles
- D. Purge Key Figure Data
Answer: B,D
NEW QUESTION 63
Which of the following functional areas are included in the out-of-the-box SAP Integrated Business Planning application for sales and operations? Note: There are 3 correct Answers to this question.
- A. Demand-driven materials requirement planning
- B. Rough-cut supply planning
- C. Executive review
- D. Consensus demand planning
- E. Finite resource capacities planning
Answer: B,C,D
NEW QUESTION 64
What are some of the available ABC segmentation methods in IBP? Note: There are 2 correct Answers to this question.
- A. By Pareto Principle (Sorted and Calculated Values)
- B. By Pareto Principle (Sorted and Cumulated %)
- C. By Number of Items (Sorted Average)
- D. By Number of Items (Sorted Values)
Answer: A,D
NEW QUESTION 65
What is a prerequisite for modeling outsourced manufacturers with production capacity using the Supply Optimizer?
- A. Use production lead times and offsets to manage components at the outsourced manufacturing location
- B. Ensure that the outsourced manufacturing locations have a separate subnetwork
- C. Model target inventory and stocks at the outsourced manufacturing location
- D. Model relative production costs across internal locations and outsourced manufacturing locations
Answer: D
NEW QUESTION 66
What setting is mandatory in the Manage Lifecycle Planning app when introducing a new product?
- A. Define at least one attribute of the planning area which represents the Product ID
- B. Define which is the attribute ID for the Lifecycle profiles
- C. Define which phase-in and phase-out profiles can be used within Lifecycle Planning
- D. Define which key figure can be used as sales history for new products
Answer: D
NEW QUESTION 67
Time profiles are made out of levels, which are in turn made out of periods. What are the ways SAP IBP identifies profiles and periods? Note: There are 2 correct answers to this question.
- A. Both periods and profiles are referenced with start and end dates.
- B. Periods are identified by an alphanumeric prefix and profiles by an integer.
- C. Periods are identified by an integer and profiles by an alphanumeric prefix.
- D. Both periods and profiles are identified by an integer.
Answer: B,C
NEW QUESTION 68
You need to create time periods for the time profile in a planning are
a. What should you be aware of when executing the Create Time Periods application job?
- A. This application job can be run for multiple time profiles at once.
- B. The planning area with this time profile must be activated so that the application job can proceed.
- C. This application job cannot be scheduled for immediate start.
- D. A time profile has to be activated so that the application job can proceed.
Answer: B
NEW QUESTION 69
Forecast Error CV is an input to which of the following?
- A. Calculate Target Inventory Components in Inventory Planning Profile Operator
- B. Forecast Error Calculation in Inventory Planning Profile Operator
- C. Multistage Inventory Optimization in Inventory Planning Profile Operator
- D. Time-Series-Based Supply Planning Optimizer
Answer: C
NEW QUESTION 70
Which of the following approaches could you take to reduce run times of an optimizer? Note: There are
2 correct Answers to this question.
- A. Increase the use of incremental lot size beyond the frozen horizon.
- B. Split into multiple planning areas to support weekly vs. daily planning needs.
- C. Use a subnetwork ID to reduce the size of the problem.
- D. Avoid using telescopic time buckets.
Answer: C,D