Scrum PSM-I (Professional Scrum Master I) Exam is a globally recognized certification that validates the knowledge and skills of professionals in the field of Scrum methodology. PSM-I exam is designed to test the understanding of the Scrum framework, roles, events, artifacts, and the principles behind them. It is a challenging and rigorous exam that requires a deep understanding of the Scrum framework and its application in real-world scenarios.

 

NEW QUESTION # 26
Which of the following are true about the Product Owner role? (Choose two.)

  • A. The Product Owner role can be played by a committee or a team of people.
  • B. The Product Owner is accountable for ordering the Product Backlog.
  • C. The Product Owner is one person.
  • D. Multiple people can share the Product Owner role on a Scrum Team.

Answer: B,C


NEW QUESTION # 27
How do you know that a Development Team is cross-functional?

  • A. There are no conflicts within the Development Team.
  • B. Every member of the Development Team is able to perform every task.
  • C. A few of the Development Team members pair program and do Test Driven Development.
  • D. Development Team has all the skills to create a potentially releasable increment by the end of every Sprint.

Answer: D

Explanation:
According to the Scrum Guide, a Development Team is cross-functional if it has all the skills to create a potentially releasable Increment by the end of every Sprint. The other options are not indicators of cross-functionality, as they are either specific practices (such as pair programming or test driven development) or irrelevant factors (such as conflicts within the team or ability to perform every task).


NEW QUESTION # 28
A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component.Without that component there won't be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help. What would be good advice to give the Product Owner?

  • A. Tell the Product Owner that his primary concern isthe flow of value reflected in the ordering of the Product Backlog.
  • B. Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Development Team.
  • C. Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.

Answer: A


NEW QUESTION # 29
Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)

  • A. The value of work currently represented in the Product Backlog.
  • B. Team relations
  • C. Definition of Done.
  • D. How the Scrum Team does its work.
  • E. Arranging the Sprint Backlog for the next Sprint.

Answer: A,B,D


NEW QUESTION # 30
Which of the following are true about the length of the Sprint? (Choose two.)

  • A. It is best to have Sprints of consistent length throughout a development effort.
  • B. Sprint length is determined during Sprint Planning, and should be long enough to make sure the
    Development Team can deliver what is to be accomplished in the upcoming Sprint.
  • C. All Sprints must be 1 month or less.
  • D. The length of the Sprint should be proportional to the work that is done in between Sprints.
  • E. Sprint length is determined during Sprint Planning, and should hold the time it will take to code the
    planned features in the upcoming Sprint, but does not include time for any testing.

Answer: A,C


NEW QUESTION # 31
What is the recommended size for a Development Team?

  • A. 9.
  • B. 7 plus or minus 3.
  • C. 3 to 9.
  • D. At least 7.

Answer: C

Explanation:
The correct answer is D, because the recommended size for a Development Team is 3 to 9 members. The Scrum Guide states that "fewer than three Development Team members decrease interaction and results in smaller productivity gains. Smaller Development Teams may encounter skill constraints during the Sprint, causing the Development Team to be unable to deliver a potentially releasable Increment. Having more than nine members requires too much coordination. Large Development Teams generate too much complexity for an empirical process to be useful."


NEW QUESTION # 32
When does the second Sprint start? (Choose the best answer.)

  • A. After the customer completes acceptance testing of the first Sprint.
  • B. After the Product Backlog for the second Sprint has been selected.
  • C. Once the architectural changes for the second Sprint have been approved by the senior architect.
  • D. Immediately after the first Sprint.

Answer: D


NEW QUESTION # 33
What is the recommended size for a Development Team?

  • A. 9.
  • B. 7 plus or minus 3.
  • C. 3 to 9.
  • D. At least 7.

Answer: C


NEW QUESTION # 34
The Product Backlog is ordered by:

  • A. Items are randomly arranged.
  • B. Size, where small items are at the top and large items are at the bottom.
  • C. Risk, where safer items are at the top, and riskier items are at the bottom.
  • D. The Product Owner with the most valuable items placed at the top.

Answer: D


NEW QUESTION # 35
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

  • A. No, that is far too hard and must be done in a hardening Sprint.
  • B. No, each Scrum Team stands alone.
  • C. Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
  • D. Yes, but only for Scrum Teams whose work has dependencies.

Answer: C

Explanation:
The correct answer is B, because the Scrum Guide states that "at the end of a Sprint, the new Increment must be 'Done,' which means it must be in useable condition and meet the Scrum Team's definition of 'Done'. An increment is a body of inspectable, done work that supports empiricism at the end of the Sprint. The increment is a step toward a vision or goal." Therefore, all the increments from different Scrum Teams working on the same product should be integrated every Sprint to enable inspection and adaptation by the Product Owner and stakeholders.


NEW QUESTION # 36
Who is responsible for managing the progress of work during a Sprint?

  • A. The most junior member of the Team.
  • B. The Scrum Master.
  • C. The Product Owner.
  • D. The Development Team.

Answer: D

Explanation:
The correct answer is B, because the Development Team is responsible for managing the progress of work during a Sprint. The Scrum Guide states that "the Development Team tracks this total work remaining at least for every Daily Scrum to project the likelihood of achieving the Sprint Goal. By tracking the remaining work throughout the Sprint, the Development Team can manage its progress."


NEW QUESTION # 37
True or False A high-performance scrum Team ensures that each increment is complete by running a Release Sprint.

  • A. True
  • B. False

Answer: B

Explanation:
According to the Scrum Guide, a high-performance Scrum Team does not run a Release Sprint, as this is not a Scrum event. A Release Sprint is a term used to describe a Sprint that is dedicated to finalizing the product for release, such as fixing bugs, polishing features, or integrating components. This is contrary to the Scrum principle of delivering a potentially releasable Increment at the end of each Sprint, regardless of whether it is actually released or not. Therefore, the answer is false.


NEW QUESTION # 38
Why does the Product Owner want the Development Team to adhere to its definition of "Done"?

  • A. To be able to reprimand the team when they don't meet their velocity goal for the Sprint.
  • B. To predict the team's productivity over time.
  • C. To have complete transparency into what has been done at the end of each Sprint.
  • D. To know what the team will deliver over the next three Sprints.

Answer: C

Explanation:
According to the Scrum Guide1, the definition of "Done" is a formal description of the state of the Increment when it meets the quality measures required for the product. The definition guides the Development Team in creating a "Done" Increment. The definition of "Done" is created by the development organization (or Development Team if none is available from the development organization). The definition of "Done" may vary significantly per Scrum Team, depending on the context. One aspect of Scrum Teams inspecting how they work toward their Product Goal is that they improve their definition of "Done" over time. Therefore, one reason why the Product Owner wants the Development Team to adhere to its definition of "Done" is to have complete transparency into what has been done at the end of each Sprint.


NEW QUESTION # 39
Which two activities will a Product Owner engage in during a Sprint? (Choose the best two answers.)

  • A. Work with the stakeholders.
  • B. Update the Sprint burndown chart.
  • C. Answer questions from the Development Team about items in the current Sprint.
  • D. Run the Daily Scrum.
  • E. Prioritize the Development Team's work on the Sprint Backlog.

Answer: A,C


NEW QUESTION # 40
What is the typical size for a Scrum Team?
(choose the best answer)

  • A. 10 or fewer.
  • B. 0
  • C. 7 plus or minus 3.
  • D. At least 7.

Answer: A

Explanation:
The correct answer is D. 10 or fewer. According to the Scrum Guide 20201, "The Scrum Team is small enough to remain nimble and large enough to complete significant work within a Sprint, typically 10 or fewer people." The other options are outdated or incorrect. Option A was based on the previous version of the Scrum Guide, which suggested a range of 3 to 9 developers2. Option B is too vague and does not account for the upper limit of team size. Option C is too specific and does not allow for flexibility.


NEW QUESTION # 41
How do you know that a Development Team is cross-functional?

  • A. There are no conflicts within the Development Team.
  • B. Every member of the Development Team is able to perform every task.
  • C. A few of the Development Team members pair program and do Test Driven Development.
  • D. Development Team has all the skills to create a potentially releasable increment by the end of every Sprint.

Answer: D


NEW QUESTION # 42
What are three ways Scrum promotes self-organization? (Choose three.)

  • A. By not allowing documentation.
  • B. By being a lightweight framework.
  • C. By preventing stakeholders from entering the development room.
  • D. By removing titles for Development Team members.
  • E. By the Development Team deciding what work to do in a Sprint.

Answer: B,D,E


NEW QUESTION # 43
An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

  • A. Without a new vocabulary as a reminder of the change, very little change may actually happen.
  • B. The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.
  • C. All answers apply.
  • D. Management may feel less anxious.

Answer: C

Explanation:
According to the Scrum Guide, changing the terminology of Scrum may have negative consequences, such as losing the benefits of Scrum, not understanding what has changed, or having very little change at all. Therefore, all answers apply to this question. The Scrum Guide recommends using the same terminology as in the guide to avoid confusion and misunderstanding.


NEW QUESTION # 44
At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of "Done". What two things should happen with the undone Product Backlog item? (Choose two.)

  • A. If the stakeholders agree, the Product Owner can accept it and release it to the users.
  • B. Do not include the item in the Increment this Sprint.
  • C. Review the item, add the "Done" part of the estimate to the velocity and create a Story for the remaining work.
  • D. Put it on the Product Backlog for the Product Owner to decide what to do with it.

Answer: B,D

Explanation:
According to the Scrum Guide1, the definition of "Done" is a formal description of the state of the Increment when it meets the quality measures required for the product. The definition guides the Development Team in creating a "Done" Increment. The definition of "Done" is created by the development organization (or Development Team if none is available from the development organization). The definition of "Done" may vary significantly per Scrum Team, depending on the context. One aspect of Scrum Teams inspecting how they work toward their Product Goal is that they improve their definition of "Done" over time. Therefore, if a Product Backlog item worked on during the Sprint does not meet the definition of "Done", two things that should happen with the undone Product Backlog item are:
Put it on the Product Backlog for the Product Owner to decide what to do with it, as they are accountable for effective Product Backlog management and ordering.
Do not include the item in the Increment this Sprint, as it does not meet the quality standards and may compromise value.
The other options are not appropriate, as they may compromise transparency, inspection, or adaptation.


NEW QUESTION # 45
What is the role of management in Scrum?

  • A. To continually monitor staffing levels of the Development Team.
  • B. To identify and remove people that aren't working hard enough.
  • C. To monitor the Development Team's productivity.
  • D. To facilitate the Scrum Teams with insights and resources that help them improve.

Answer: D

Explanation:
The correct answer is A, because the role of management in Scrum is to facilitate the Scrum Teams with insights and resources that help them improve. The Scrum Guide states that "the organization respects their self-organization by not telling them how they should do their work." Therefore, management should support the Scrum Teams by providing them with an environment that fosters collaboration, learning, and innovation.


NEW QUESTION # 46
Which two things are appropriate for a Scrum Master to do if the Development Team doesn't have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)

  • A. Encourage the Product Owner to accept partially "Done" increments until the situation improves.
  • B. Declare the Development Team not ready for Scrum.
  • C. Have the Development Team establish a Definition of "Done" that is actually possible to achieve given current circumstances.
  • D. Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of "Done" accordingly.
  • E. Refocus the current Sprint on establishing the Development Team's infrastructure instead of delivering an increment.

Answer: C,D

Explanation:
According to the Scrum Guide1, the definition of "Done" is a formal description of the state of the Increment when it meets the quality measures required for the product. The definition guides the Development Team in creating a "Done" Increment. The definition of "Done" is created by the development organization (or Development Team if none is available from the development organization). The definition of "Done" may vary significantly per Scrum Team, depending on the context. One aspect of Scrum Teams inspecting how they work toward their Product Goal is that they improve their definition of "Done" over time. Therefore, two things that are appropriate for a Scrum Master to do if the Development Team doesn't have the engineering tools and infrastructure to completely finish each selected Product Backlog item are:
Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of "Done" accordingly.
Have the Development Team establish a Definition of "Done" that is actually possible to achieve given current circumstances.


NEW QUESTION # 47
Which two things are appropriate for a Scrum Master to do if the Development Team doesn't have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose the best two answers.)

  • A. Encourage the Product Owner to accept partially "Done" increments until the situation improves.
  • B. Declare the Development Team not ready for Scrum.
  • C. Have the Development Team establish a Definition of "Done" that is actually possible to achieve given current circumstances.
  • D. Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of "Done" accordingly.
  • E. Refocus the current Sprint on establishing the Development Team's infrastructure instead of delivering an increment.

Answer: C,D


NEW QUESTION # 48
Which statement best describes a Product Owner's responsibility?

  • A. Managing the project and ensuring that the work meets the commitments to the stakeholders.
  • B. Directing the Development Team.
  • C. Optimizing the value of the work the Development Team does.
  • D. Keep stakeholders from distracting the Development Team.

Answer: C

Explanation:
According to the Scrum Guide1, ordering Product Backlog items is solely up to the Product Owner's discretion. The Product Owner orders items in the Product Backlog to best achieve goals and missions. To do this, they optimize value by considering various factors such as cost and benefit, risk, dependencies, date needed, etc. The Product Owner is responsible for maximizing the value of the work the Development Team does.


NEW QUESTION # 49
......


Understanding functional and technical aspects of Scrum Master PSM I Exam Scrum Framework

The following will be discussed here:

  • Done
  • Artifacts
  • Understanding and Applying the Scrum Framework Empiricism
  • Scrum Values

 