NEW QUESTION 38
Which of the following should a PV installer do during dc insulation resistance testing?
- A. Close ac and dc disconnects and have the system running for at least 5 minutes before testing.
- B. Remove surge suppression equipment from the circuit being tested.
- C. Wait until is raining and all wiring is damp to conduct the test.
- D. Connect the megohmmeters's negative terminal to the dc circuit insulation
Answer: D
NEW QUESTION 39
A PV technician is installing a 6.5KWac inverter using a 40A backfed breaker. The single line shows a 200A panelboard with a 200A breaker, but the installer finds that the panelbord actually has a 150A main breaker.
Which of the following is the CORRECT installation option?
- A. Complete the installation as noted above.
- B. Replace the 200A panel with a 150A panel.
- C. Install a 30A backfed circuit breaker.
- D. Change the main circuit breaker to a 200A unit.
Answer: A
NEW QUESTION 40
The AHJ for enforcement of the NEC has which responsibility?
- A. Inspecting factory-installed wire and equipment construction methods
- B. Inspecting installations under the exclusive control of the electric utility
- C. Making interpretations of the rules and deciding on approval of equipment and material
- D. Approval equipment installation methods for efficiency, convenience, and adequacy for good service
Answer: C
NEW QUESTION 41
The following dc portion of a PV schematic (functionally grounded conductor not shown) is submitted to the building official for permit approval. The building official, who also is he AHJ, allow the system to be installed by requiring what NEC-required MINIMUM size equipment grounding conductor at Location A?
- A. #12 aluminum
- B. #6 aluminum
- C. #10 copper
- D. #8 copper
Answer: C
NEW QUESTION 42
An installer has decided to use 31 in. long. 3.1/2 in diameter conical ground screws as the footings for a
3.840W solar electric system. Access to he is too difficult to pour concrete footings. The soll is classified as sandy loam. The design wind speed is 90 mph with an uplift force of 32 ibs/ft2. What is the MINIMUM number of screw required to resist uplift loads?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
NEW QUESTION 43
A PV system equipped with rapid shutdown requires a label stating ''RAPID SHUTDOWN SWITCH FOR SOLAR PV SYSTEM''.
Which is the BEST description of where this label is required?
- A. On or within 3 ft. of the ac disconnect
- B. On or within 3 ft. of the ac disconnect
- C. On or within 3 ft. of the ac disconnect
- D. On or within 3 ft. of the ac disconnect
Answer: D
NEW QUESTION 44
A PV array with 58 in. X 38 in modules in portrait orientation is to be mounted at a 35 tiit angle on a shingle roof that has a 5:12 pitch. Assuming the support leg is attached to the top of the modules and is perpendicular to its face, what is the length of the support leg for the modules?
- A. 40.50 in.
- B. 12.73 in.
- C. 18.25 in.
- D. 24.24 in.
Answer: B
NEW QUESTION 45
A ground resistance measurement on a newly installed grounding electrode indicates a resistance of 130. The earth connection may be improved by connecting the existing electrode to a:
- A. Supplemental grounding electrode located 5 ft, away.
- B. Supplemental copper plated steel grounding electrode located 8 ft, away.
- C. Supplement 1/4 in, in thick aluminumplate electrode buried 30 in. down and located 7 ft, away.
- D. Buried water piping system using 40 ft. of 2 in. PVC piping located 10 ft awat.
Answer: B
NEW QUESTION 46
Which load path connections need to be analyzed when determining live and dead loads on a PV array system installed directly to a metal seam roof?
- A. Rail to metal seam roof, metal seam roof to top plate, top plate to wall system
- B. Module to rail, rail to roof sheathing, roof sheathing to wall, wall to base plate/foundation system
- C. Module to rail to metal seam roof, metal seam roof to top plate system
- D. Module to rail to metal seam roof, metal seam roof sheathing/rather system.
Answer: D
NEW QUESTION 47
An 8KWsc roof-mounted array is placed on a school building. The inverter is located within 1 ft, of the array boundary and has an integrated ac-and dc-disconnecting switch. The system is to be connected to a 400A load center, protected by a 400A main breaker. Which of the following MUST be included to meet NEC requirements?
- A. An ac-disconnect label with the location of the rooftop dc-disconnect switch.
- B. A readily accessible dc disconnect with rapid shutdown initiation device permanently labeled
- C. A readily accessible ac-disconnecting switch, who location is identified on the system directory
- D. A rapid shutdown initiationdevice operating contractor within 1 ft, of the array to de-energize the dc subarrays
Answer: C
NEW QUESTION 48
A 1. 100 ft, 2 ranch home with cathedralcallingshas a 14 ft. x 41 ft. 8 in , south-facing , composite shingle roof. An engineer has determined that the home's 2 in, x 6 in. on-center roof rafters are strong enough to gold a solar electric system. The system will have 62.25 in. x 32.50 in. modules with a 1-in gap between modules and a standard twin-rillmounting system number of modules that can fit on the roof on under these conditions?
- A. 40 modules in landscape
- B. 28 modules in portrait
- C. 30 modules in portrait
- D. 35 modules in landscape
Answer: D
NEW QUESTION 49
With all other environmental parameters being the same, which would be the expected reduction in KM performance of a PV system after an irradiance drop from 810w/m2 to 740w/m2?
- A. 10.2%
- B. 8.6%
- C. 9.5%
- D. 7.4%
Answer: B
NEW QUESTION 50
Which of the following is an NEC-indicate means to identify PV source and output circuits at accessible points of termination connection, and splices?
- A. Placards
- B. Conduct stickers
- C. Insulation type
- D. Tagging
Answer: D
NEW QUESTION 51
Which insulation color is allowed for a current-carrying roottop dc conductor on a functionally grounded 6kw PV system?
- A. White
- B. Red
- C. Green/yellow
- D. Green
Answer: B
NEW QUESTION 52
Aerial lifts used to hoist equipment and PV modules to roof levels may be fieldmodifiedfor uses other than those intended by the manufacturer with which approval or certification?
- A. Approval by the local AHJ for meeting safely regulations
- B. Tested and approval by the distributor of the equipment
- C. Certified via the state material handling safely statutes
- D. Certified in writing by the manufacturer or an NRTL
Answer: A
NEW QUESTION 53
Inspection of a new PV installation shows that the dwelling uses a galvanized water pipe for its grounding electrode and that the PV system now shares the connection. Which of the following is an acceptable supplemental electrode method to ensure the integrity of having a grounding electrode?
- A. Connecting the water pipe to the service entrance panel metal structure
- B. Connecting the water pipe to a gas pipe that is known to be solidly grounded
- C. Connecting the service panel to an auxiliary ground used by a lightning protection system
- D. Connection the service panel to a copper-clad steel ground rod near the panel
Answer: A
NEW QUESTION 54
A homeowner is concerned that a 6kWdc PV system might be experiencing a performance issue. The homeowner has noticed what appears to be declining production. The installer analyzes the following data acquisition system (DAS) results for each year since the installation:
Given the data, which is the MOST likely conclusion to draw?
- A. There is a problem with the DAS because the peak sun hours do not correlate with production values and the das should be repaired.
- B. The system has experienced above-average degradation and a module warranty claim should be explored.
- C. There is an intermittent inverter failure that is causing production to be lower than expected and the inverter should be repaired.
- D. A combination of normal module degradation combined with cloudy weather has caused lower output in the past few years.
Answer: D
NEW QUESTION 55
An installer is using 1/2 in lag boits to secure roof-monitoring hardware to rafters through a roof deck. Which of the following should the installer predrill?
- A. A pilot hole one-half the length of the bolt
- B. A 5/16 in pilot hole through the roof into the rafter
- C. A 1/8 in, pilot hole through the roof into the rafter
- D. A pilot hole one-fourth the length of the bolt
Answer: B
NEW QUESTION 56
Thermal imaging infrared cameras can be used to help find which of the following system operational issues?
- A. Blind spot fault in a source circuit
- B. Battery state of charge in a multimode system
- C. Loose PV input circuit terminations in a combiner box
- D. Intensity of solar insolation to determine power output
Answer: A
NEW QUESTION 57
A dwelling has a 200A main load center with a 150 main breaker. Which of the following is the MOST powerful 240V inverter that can be installed in the house using the existing main panelboard with a backfed breaker?
- A. 21, 600W
- B. 7, 689W
- C. 17, 280W
- D. 9, 600W
Answer: C
NEW QUESTION 58
An installer is hired to troubleshoot a 10-year-old roottop system with open-circuitvoltage of 300V. The ground-fault detection (GFD) device has tripped. The insulation on the exposed source circuit cables has deterlorated with multiple cracks and has no flexibility. Which concern is the MOST likely safely issue when servicing this array?
- A. Insulation has become an electrical conductor since it has changed its composition.
- B. Short-circuit current is present at the PV source-circuit terminals of the disconnect device because of electrical leakage.
- C. Ungrounded conductors are conducing current event the ground-fault device has activated.
- D. Cracked insulation has allowed water intrusion that resulted in oxidation of the copper conductors.
Answer: A
NEW QUESTION 59
According to the NEC, if the PV system disconnect and the building service disconnect are at different locations, there MUST be a/an:
- A. Means of locking out both disconnects when the PV system inverter is being serviced.
- B. Permanent plaque or directory that indicates the location of thePV utility connection.
- C. Interface that shuts down the PV system if the utility connection is lost.
- D. Permanent plaque or directory that indicates the locations of both disconnects.
Answer: D
NEW QUESTION 60
A connector not listed to be used in a concealed location and being used as a disconnect for PV equipment shall comply with which of the following?
- A. The grounding member shall be last to make and first to break contact with the mating connector
- B. The grounding member shall be interconnectchangeable with receptacles in other electrical systems.
- C. The connector shall have a non-polarized configuration.
- D. The connector shall be installed so as to guard against inadvertent with live parts by persons.
Answer: D
NEW QUESTION 61
The point-of-utility connection of a residential utility-interactive PV system is in the main distribution panel. If the busbars of the main distribution panel are rated at 200A, and if the distribution panel has a 200A main breaker, the rated output current of the inverter cannot exceed.
- A. 32A
- B. 40A
- C. 200A
- D. 24A
Answer: A
NEW QUESTION 62
A PV system is located at 41 N latitude. The sun angle is 23 on December 21 at solar noon. Assuming that the
65 ft tree is directly south of the PV array and will grow 20 ft. over the life of the PV system, what is the MNIMUM distance the tree to the button of the prevent shading?
- A. 98 ft.
- B. 153 ft.
- C. 201 ft.
- D. 167 ft.
Answer: C
NEW QUESTION 63
......
Valid Way To Pass NABCEP's PVIP Exam with : https://www.exams4collection.com/PVIP-latest-braindumps.html
Free Test Engine For PV Installation Professional (PVIP) Board Certification Certification Exams: https://drive.google.com/open?id=11Rp4CnbXUQlPQe4aY5nptXyK_-qntvj7