NEW QUESTION # 17
As a NACE Level 2 Inspector on a field job; prior to submission your documentation should always reviewed and approved by:
- A. Another NACE Level 2 Inspector
- B. A NACE Level 3 Inspector
- C. A NACE Level 1 Inspector
- D. A NACE Protective Coating Specialist
Answer: B
NEW QUESTION # 18
Coating surveys may include which steps?
Select All That Apply:
- A. Schedule the remedial work
- B. Summarize the collected data
- C. Evaluate the coatings performance
- D. Develop a survey plan
Answer: A,B,C,D
NEW QUESTION # 19
When performing testing in accordance with ASTM D 2583 the inspector may observe:
- A. Cold flow or creep
- B. Cohesion failure
- C. Adhesion failure
- D. Glue failure
Answer: A
NEW QUESTION # 20
Coating application to concrete substrates is:
- A. Not required as Concrete is inorganic
- B. More challenging than coating steel
- C. The same as coating steel
- D. Less challenging, than coating steel
Answer: B
NEW QUESTION # 21
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
- A. True
- B. False
Answer: A
NEW QUESTION # 22
You are the NACE Coating Inspector on a tank lining project and are asked to perform a high voltage holiday test after the coating applicators have completed their final repairs. After meeting all the confined space entry permit you enter the tank and notice a very strong odor of solvent.
Your first course of action should to:
- A. Exit the tank and document the incident in your daily report
- B. Exit the tank and immediately and report the problem to the nearest safety supervisor
- C. Don your air supplied respirator and continue the testing
- D. Investigate to find the source of the odor
Answer: B
NEW QUESTION # 23
You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value.
As this is not part of the standard you should:
- A. Ignore the additional requirement
- B. Call your supervisor
- C. Request clarification from the specifier
- D. Enforce the additional requirement
Answer: D
NEW QUESTION # 24
Dehumidification is defined as the removal of moisture vapor from the air to
- A. lower its dew point,
- B. lower its temperature
- C. provide worker comfort.
- D. raise its relative humidity.
Answer: A
NEW QUESTION # 25
The solvent sensitivity/solvent wipe test (ASTM D4752) is used to determine the cure of
- A. epoxies.
- B. powder coatings.
- C. urethanes.
- D. inorganic zincs.
Answer: D
NEW QUESTION # 26
Because a NACE Level 2 Inspector has been trained in specific destructive tests, it is up to the Inspector to decide if and when a destructive test is required.
- A. False
- B. True
Answer: A
NEW QUESTION # 27
The cost of qualified Coating Inspection is normally offset by:
- A. Lower Coating Life Cycle Costs
- B. Lower Supervision Costs
- C. Lower Safety Enforcement Costs
- D. Lower Application Costs
Answer: A
NEW QUESTION # 28
The Inspectors' goal at the Pre-Job Conference is to:
- A. Obtain a clear understanding of the Specification
- B. Take accurate meeting minutes for distribution
- C. Manage the meeting so it doesn't go off topic
- D. Discuss contractual requirements
Answer: A
NEW QUESTION # 29
The HATE adhesion tester uses
- A. compressed air to apply pressure to the test dolly.
- B. a special tape to apply pressure to the test dolly.
- C. mechanical means only to apply pressure to the test dolly.
- D. a hydraulic piston to apply pressure to the test dolly.
Answer: D
NEW QUESTION # 30
Linings are used on the interior of pipelines to
- A. provide protection against soil chemicals.
- B. protect the transported product.
- C. afford limited temperature insulation.
- D. reduce magnetic polarity.
Answer: B
NEW QUESTION # 31
Coating Surveys are legally required:
- A. On high pressure gas lines and fireproofed structures
- B. On food and beverage vessels and can linings
- C. On commercial marine vessels and offshore platforms
- D. On water tanks and potable water pipelines
Answer: C
NEW QUESTION # 32
When ASIN D 3363 is specified the Inspector must:
- A. Record the two end points identified in the standard
- B. Record the highest value attained
- C. Use the correct solvent
- D. Record the percentage of failure
Answer: A
NEW QUESTION # 33
Inspection and Test plans are developed by referencing:
- A. The Specification, SDS, relevant Standards and Codes
- B. The Specification, Safety Manual, Relevant Standards and Codes
- C. The Specification, TDS, relevant Standards and Codes
- D. The Specification, Application Guidelines, 'Relevant Standards and Codes
Answer: C
NEW QUESTION # 34
......